KERRY County Council will supply 12o new housing units by the end of the summer.

At the March meeting of Tralee Municipal District of Kerry County Council, Labour Cllr. Terry O’ Brien asked the Council to confirm the number of houses currently being built in Tralee MD by the Local Authority and when they would be available for renting.

In reply, Kerry County Council supplied the construction projects in the Tralee MD and estimated completion dates.

Continued below…

.

They are…

• Rahoonane, Tralee – 8 units, estimated to be completed by July 2022
• Ballyrickard, Tralee – 21 units, estimated to be completed by May 2022
• Croogorts, Tralee – 30 units, estimated to be completed by Aug 2022
• Lohercannon, Tralee – 61 units, estimated to be completed by Aug 2022